(ISC)2(ISC)2
CAP · Question #164
CAP Question #164: Real Exam Question with Answer & Explanation
The correct answer is B: It is a risk that remains after planned risk responses are taken.. See the full explanation below for the reasoning.
Security and Privacy Governance, Risk Management, and Compliance Program
Question
You work as a project manager for BlueWell Inc. You with your team are using a method or a (technical) process that conceives the risks even if all theoretically possible safety measures would be applied. One of your team member wants to know that what is a residual risk. What will you reply to your team member?
Options
- AIt is a risk that remains because no risk response is taken.
- BIt is a risk that remains after planned risk responses are taken.
- CIt is a risk that can not be addressed by a risk response.
- DIt is a risk that will remain no matter what type of risk response is offered.
Topics
#Residual Risk#Risk Management#Risk Response
Community Discussion
No community discussion yet for this question.