CAP · Question #163
In what portion of a project are risk and opportunities greatest and require intense planning and anticipation of risk events?
The correct answer is D. Initiating. During the Initiating phase, uncertainty is at its highest because the least is known about the project. Since risk is directly tied to uncertainty, both threats and opportunities are greatest at this point. As the project progresses through Planning, Executing, and Closing…
Question
In what portion of a project are risk and opportunities greatest and require intense planning and anticipation of risk events?
Options
- APlanning
- BExecuting
- CClosing
- DInitiating
How the community answered
(35 responses)- B6% (2)
- C3% (1)
- D91% (32)
Explanation
During the Initiating phase, uncertainty is at its highest because the least is known about the project. Since risk is directly tied to uncertainty, both threats and opportunities are greatest at this point. As the project progresses through Planning, Executing, and Closing, more information becomes available, uncertainty decreases, and so does risk exposure. This is why early stakeholder engagement, feasibility analysis, and high-level risk identification during initiation are so critical. By the time the project reaches Closing, most risks have either been resolved or have materialized.
Topics