CAP · Question #135
Your organization has named you the project manager of the JKN Project. This project has a BAC of $1,500,000 and it is expected to last 18 months. Management has agreed that if the schedule baseline…
The correct answer is A. Project costs will increase. Crashing is a schedule compression technique where additional resources (money, personnel, equipment) are added to critical path activities to shorten the project duration. Because you are adding resources - such as overtime pay, additional staff, or expedited delivery of…
Question
Your organization has named you the project manager of the JKN Project. This project has a BAC of $1,500,000 and it is expected to last 18 months. Management has agreed that if the schedule baseline has a variance of more than five percent then you will need to crash the project. What happens when the project manager crashes a project?
Options
- AProject costs will increase.
- BThe amount of hours a resource can be used will diminish.
- CThe projectwill take longer to complete, but risks will diminish.
- DProject risks will increase.
How the community answered
(19 responses)- A84% (16)
- B5% (1)
- D11% (2)
Explanation
Crashing is a schedule compression technique where additional resources (money, personnel, equipment) are added to critical path activities to shorten the project duration. Because you are adding resources - such as overtime pay, additional staff, or expedited delivery of materials - project costs will increase. Crashing does not reduce risks (it may introduce new ones), does not make the project take longer, and does not diminish resource hours. The fundamental trade-off in crashing is: reduced schedule duration at the expense of increased cost.
Topics
Community Discussion
No community discussion yet for this question.