nerdexam
(ISC)2

CAP · Question #135

Your organization has named you the project manager of the JKN Project. This project has a BAC of $1,500,000 and it is expected to last 18 months. Management has agreed that if the schedule baseline…

The correct answer is A. Project costs will increase. Crashing is a schedule compression technique where additional resources (money, personnel, equipment) are added to critical path activities to shorten the project duration. Because you are adding resources - such as overtime pay, additional staff, or expedited delivery of…

Security and Privacy Governance, Risk Management, and Compliance Program

Question

Your organization has named you the project manager of the JKN Project. This project has a BAC of $1,500,000 and it is expected to last 18 months. Management has agreed that if the schedule baseline has a variance of more than five percent then you will need to crash the project. What happens when the project manager crashes a project?

Options

  • AProject costs will increase.
  • BThe amount of hours a resource can be used will diminish.
  • CThe projectwill take longer to complete, but risks will diminish.
  • DProject risks will increase.

How the community answered

(19 responses)
  • A
    84% (16)
  • B
    5% (1)
  • D
    11% (2)

Explanation

Crashing is a schedule compression technique where additional resources (money, personnel, equipment) are added to critical path activities to shorten the project duration. Because you are adding resources - such as overtime pay, additional staff, or expedited delivery of materials - project costs will increase. Crashing does not reduce risks (it may introduce new ones), does not make the project take longer, and does not diminish resource hours. The fundamental trade-off in crashing is: reduced schedule duration at the expense of increased cost.

Topics

#Project Management#Project Crashing#Cost Management#Schedule Management

Community Discussion

No community discussion yet for this question.

Full CAP Practice