nerdexam
(ISC)2

CAP · Question #136

You work as a project manager for BlueWell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decided, with your stakeholders' approval, to fast…

The correct answer is C. Risks. Fast tracking is a schedule compression technique where activities normally performed sequentially are instead performed in parallel or with overlapping timelines. This approach does not necessarily increase costs or human resource needs significantly. However, because work is…

Security and Privacy Governance, Risk Management, and Compliance Program

Question

You work as a project manager for BlueWell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decided, with your stakeholders' approval, to fast track the project work to get the project done faster. When you fast track the project which of the following are likely to increase?

Options

  • AQuality control concerns
  • BCosts
  • CRisks
  • DHuman resource needs

How the community answered

(58 responses)
  • A
    7% (4)
  • B
    3% (2)
  • C
    78% (45)
  • D
    12% (7)

Explanation

Fast tracking is a schedule compression technique where activities normally performed sequentially are instead performed in parallel or with overlapping timelines. This approach does not necessarily increase costs or human resource needs significantly. However, because work is overlapping, there is a greater chance that upstream decisions will affect downstream work that has already started, leading to rework and coordination issues. This overlap inherently increases project risk. Quality concerns are a side effect of rework, not a direct primary increase; risk is the most accurate and direct answer.

Topics

#Project Management#Fast Tracking#Risk Management#Schedule Management

Community Discussion

No community discussion yet for this question.

Full CAP Practice