If Project A has inspected 1546 requirements in 54 hours and found 441, what is the Inspection Rate for Project A?
The correct answer is A. 28.63. See the full explanation below for the reasoning.
Question
If Project A has inspected 1546 requirements in 54 hours and found 441, what is the Inspection Rate for Project A?
Options
- A28.63
- B3.05
- C20.02
- D8.17
How the community answered
(29 responses)- A76% (22)
- B3% (1)
- C14% (4)
- D7% (2)