CABA · Question #209
The challenge(s) of using the iterative development methodology is/are:
The correct answer is E. All of the above. See the full explanation below for the reasoning.
Question
The challenge(s) of using the iterative development methodology is/are:
Options
- ACommunication and coordination skills take center stage in project development
- BInformal requests for improvement after each phase may lead to confusion
- CUser community needs to be actively involved throughout the project
- DCan lead to "scope creep"
- EAll of the above
How the community answered
(35 responses)- A3% (1)
- B6% (2)
- C3% (1)
- D11% (4)
- E77% (27)