If Project A has inspected 1546 requirements in 54 hours and found 350 defects but 9 escaped, what is the Escape Rate of Project A?

The correct answer is B. 2.57%. See the full explanation below for the reasoning.

Question

If Project A has inspected 1546 requirements in 54 hours and found 350 defects but 9 escaped, what is the Escape Rate of Project A?

Options

  • A2.04%
  • B2.57%
  • C16.67%
  • D.58%

How the community answered

(14 responses)
  • A
    7% (1)
  • B
    79% (11)
  • D
    14% (2)