If Project A has inspected 1546 requirements in 54 hours and found 350 defects but 9 escaped, what is the Escape Rate of Project A?
The correct answer is B. 2.57%. See the full explanation below for the reasoning.
Question
If Project A has inspected 1546 requirements in 54 hours and found 350 defects but 9 escaped, what is the Escape Rate of Project A?
Options
- A2.04%
- B2.57%
- C16.67%
- D.58%
How the community answered
(14 responses)- A7% (1)
- B79% (11)
- D14% (2)