During the Design Phase, if there are changes in Project Scope, which documents will be impacted?

The correct answer is A. Project Plan, Requirements Documentation, Design, Test Cases. See the full explanation below for the reasoning.

Question

During the Design Phase, if there are changes in Project Scope, which documents will be impacted?

Options

  • AProject Plan, Requirements Documentation, Design, Test Cases
  • BProject Plan, Design, Test Cases
  • CRequirements Documentation, Design, Test Cases
  • DRequirements Documentation, Design, Test Cases, Code

How the community answered

(27 responses)
  • A
    85% (23)
  • B
    4% (1)
  • C
    7% (2)
  • D
    4% (1)