Which document ensures that each requirement that is captured at the beginning of the project is tracked until its implementation?

The correct answer is B. Requirement Traceability Document. See the full explanation below for the reasoning.

Question

Which document ensures that each requirement that is captured at the beginning of the project is tracked until its implementation?

Options

  • AProject Scope Document
  • BRequirement Traceability Document
  • CRequirement Document
  • DDesign Document

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    75% (21)
  • C
    14% (4)
  • D
    7% (2)