Question
The stock/requirements list for a finished product contains only one sales order and one fixed planned order with the same quantity. The availability dates for both MRP elements are on working days. The availability date for the fixed planned order is set to a later date than the one for the sales order. However, a corresponding rescheduling exception message does not appear. What could be the reasons? (Choose two)
Options
- AThe delta between the availability dates falls within the tolerance window defined in Customizing.
- BThe fixed planned order is outside the rescheduling horizon.
- CRequirements planning has not been carried out.
- DThe MRP elements are linked via fixed pegging.