In which of the following objects can you activate back flushing for production orders? (Choose three)

The correct answer is A. Work center B. Routing D. Material master (component). See the full explanation below for the reasoning.

Question

In which of the following objects can you activate back flushing for production orders? (Choose three)

Options

  • AWork center
  • BRouting
  • CMaterial master (finished product)
  • DMaterial master (component)
  • EProduction scheduling profile

How the community answered

(47 responses)
  • A
    85% (40)
  • C
    6% (3)
  • E
    9% (4)