SAP
C_TSCM42_66 · Question #73
For which of the following objects can you enter a confirmation? (Choose two)
The correct answer is B. Production order operation C. Production order. See the full explanation below for the reasoning.
Question
For which of the following objects can you enter a confirmation? (Choose two)
Options
- AWork Center
- BProduction order operation
- CProduction order
- DTrigger Point
How the community answered
(29 responses)- A10% (3)
- B83% (24)
- D7% (2)
Community Discussion
No community discussion yet for this question.