nerdexam
SAP

C_TSCM42_66 · Question #73

For which of the following objects can you enter a confirmation? (Choose two)

The correct answer is B. Production order operation C. Production order. See the full explanation below for the reasoning.

Question

For which of the following objects can you enter a confirmation? (Choose two)

Options

  • AWork Center
  • BProduction order operation
  • CProduction order
  • DTrigger Point

How the community answered

(29 responses)
  • A
    10% (3)
  • B
    83% (24)
  • D
    7% (2)

Community Discussion

No community discussion yet for this question.

Full C_TSCM42_66 Practice