C_TSCM42_66 · Question #75

C_TSCM42_66 Question #75: Real Exam Question with Answer & Explanation

Sign in or unlock C_TSCM42_66 to reveal the answer and full explanation for question #75. The question stem and answer options stay visible for context.

Question

Which issue can occur if the lot size-dependent in-house production time in the material master is not updated after changing the routing?

Options

  • ALead time scheduling cannot take place.
  • BDependent requirements request the components from the bill of materials at wrong times when using
  • CRequirements planning creates an appropriate exception message in basic dates scheduling.
  • DSubsequent capacity planning is no longer possible due to the obsolete scheduling parameters.