C_TSCM42_65 · Question #8
Which of the following statements about the planning functions available in SAP ECC are true? (Choose two.)
The correct answer is A. Master production scheduling (MPS) refers to preferred planning of important materials. B. Material requirements planning (MRP) does not include automatic capacity leveling. See the full explanation below for the reasoning.
Question
Which of the following statements about the planning functions available in SAP ECC are true? (Choose two.)
Options
- AMaster production scheduling (MPS) refers to preferred planning of important materials.
- BMaterial requirements planning (MRP) does not include automatic capacity leveling.
- CLong-term planning (LTP) is a long-term form of forecast planning.
- DIn demand management (DM) material shortage situations are identified and given requirement