C_TSCM42_65 · Question #6
When maintaining a work center, formulas can be assigned in the scheduling view. Formulas use formula parameters for calculation. What can be the origin of the formula parameters used for…
The correct answer is B. Standard value from operation in task list C. User-defined field from operation in task list D. General operation values in task list. See the full explanation below for the reasoning.
Question
When maintaining a work center, formulas can be assigned in the scheduling view. Formulas use formula parameters for calculation. What can be the origin of the formula parameters used for scheduling? (Choose three.)
Options
- AGeneral values from work scheduling view in the material master
- BStandard value from operation in task list
- CUser-defined field from operation in task list
- DGeneral operation values in task list
- EGeneral item values in bill of materials
How the community answered
(34 responses)- A15% (5)
- B79% (27)
- E6% (2)