C_TSCM42_65 · Question #162
The stock/requirements list for a finished product contains only one customer order and one fixed planned order with the same quantity. The availability dates for both MRP elements are on working…
The correct answer is C. The fixed planned order is outside the rescheduling horizon. D. The delta between the availability dates falls within the tolerance window defined in Customizing. See the full explanation below for the reasoning.
Question
The stock/requirements list for a finished product contains only one customer order and one fixed planned order with the same quantity. The availability dates for both MRP elements are on working days. The availability date of the fixed planned order is set to a later date compared to the one of the customer order. However, a corresponding rescheduling exception message does not occur. What could be the reason? (Choose two)
Options
- ARequirement planning has not been carried out.
- BThe MRP elements are linked via fixed pegging.
- CThe fixed planned order is outside the rescheduling horizon.
- DThe delta between the availability dates falls within the tolerance window defined in Customizing.
How the community answered
(41 responses)- A20% (8)
- B10% (4)
- C71% (29)