C_TSCM42_65 · Question #161

You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead- time…

The correct answer is C. In multi-level backward scheduling, dependent requirements are triggered at the start date for the planned. See the full explanation below for the reasoning.

Question

You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead- time scheduling). Which of the following statements is true for the resulting dependent requirements?

Options

  • AWhen a customer order is created for the finished material, the dependent requirements are automatically
  • BIn multi-level backward scheduling, dependent requirements are calculated to the exact second.
  • CIn multi-level backward scheduling, dependent requirements are triggered at the start date for the planned
  • DIf the individual material components are explicitly assigned to the operations of a routing, the requirement

How the community answered

(27 responses)
  • A
    7% (2)
  • B
    19% (5)
  • C
    70% (19)
  • D
    4% (1)