C_TSCM42_65 · Question #161
You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead- time…
The correct answer is C. In multi-level backward scheduling, dependent requirements are triggered at the start date for the planned. See the full explanation below for the reasoning.
Question
You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead- time scheduling). Which of the following statements is true for the resulting dependent requirements?
Options
- AWhen a customer order is created for the finished material, the dependent requirements are automatically
- BIn multi-level backward scheduling, dependent requirements are calculated to the exact second.
- CIn multi-level backward scheduling, dependent requirements are triggered at the start date for the planned
- DIf the individual material components are explicitly assigned to the operations of a routing, the requirement
How the community answered
(27 responses)- A7% (2)
- B19% (5)
- C70% (19)
- D4% (1)
Community Discussion