nerdexam
SAP

C_TSCM42_64 · Question #67

In what order are the individual steps of material requirements planning performed in SAP ECC?

The correct answer is D. 1. Net requirements calculation. See the full explanation below for the reasoning.

Question

In what order are the individual steps of material requirements planning performed in SAP ECC?

Options

  • A
    1. Net requirements calculation
  • B
    1. Availability check
  • C
    1. Calculation of safety stock
  • D
    1. Net requirements calculation

How the community answered

(55 responses)
  • A
    5% (3)
  • B
    4% (2)
  • C
    9% (5)
  • D
    82% (45)

Community Discussion

No community discussion yet for this question.

Full C_TSCM42_64 Practice