In what order are the individual steps of material requirements planning performed in SAP ECC?
The correct answer is D. 1. Net requirements calculation. See the full explanation below for the reasoning.
Question
In what order are the individual steps of material requirements planning performed in SAP ECC?
Options
- A
- Net requirements calculation
- B
- Availability check
- C
- Calculation of safety stock
- D
- Net requirements calculation
How the community answered
(55 responses)- A5% (3)
- B4% (2)
- C9% (5)
- D82% (45)