In production order processing, for which of the following objects can you enter a confirmation? (Choose three.)

The correct answer is B. Individual Capacity C. Order D. Operation / Suboperation. See the full explanation below for the reasoning.

Question

In production order processing, for which of the following objects can you enter a confirmation? (Choose three.)

Options

  • AWork Center
  • BIndividual Capacity
  • COrder
  • DOperation / Suboperation
  • ETrigger Point

How the community answered

(17 responses)
  • A
    6% (1)
  • B
    82% (14)
  • E
    12% (2)