SAP
C_TSCM42_64 · Question #26
A material was planned in the context of SAP ECC material requirements planning and the MRP controller subsequently processed the material by manually converting a specific planned order into a…
The correct answer is C. The stock/requirements list was updated at the precise time it was accessed. D. The stock/requirements list displays the production order. See the full explanation below for the reasoning.
Question
A material was planned in the context of SAP ECC material requirements planning and the MRP controller subsequently processed the material by manually converting a specific planned order into a production order. The MRP controller now accesses the current stock/requirements list and the MRP list for this material and compares the two. Which of the following statements are true for the two lists at this stage? (Choose two.)
Options
- AThe MRP list has the status "processed".
- BThe MRP list displays the production order.
- CThe stock/requirements list was updated at the precise time it was accessed.
- DThe stock/requirements list displays the production order.
How the community answered
(62 responses)- A13% (8)
- B6% (4)
- C81% (50)
Community Discussion
No community discussion yet for this question.