A final assembly process takes place at three work centers, one after the other. The routing, which consists of three associated operations (10, 20 and 30), plans for a specific BOM component to be…
The correct answer is A. 1. Create BOM 2. Create work centers 3. Create routing 4. Carry out component assignment. See the full explanation below for the reasoning.
Question
A final assembly process takes place at three work centers, one after the other. The routing, which consists of three associated operations (10, 20 and 30), plans for a specific BOM component to be installed during operation 30 and not before. The component should therefore only be requested at the start of operation 30. What sequence do you follow in master data maintenance in SAP ECC to make this component available in line with operations during final assembly? SAP C_TSCM42_64 Exam
Options
- A
- Create BOM 2. Create work centers 3. Create routing 4. Carry out component assignment
- B
- Create work centers 2. Create routing 3. Create BOM 4. Carry out component assignment
- C
- Create routing 2. Create work centers 3. Create BOM 4. Carry out component assignment in
- D
- Create BOM 2. Create work centers 3. Create routing 4. Carry out component assignment in
How the community answered
(44 responses)- A82% (36)
- B2% (1)
- C7% (3)
- D9% (4)
Community Discussion
No community discussion yet for this question.