C_TSCM42_64 · Question #1
In SAP ECC, you want to map an in-house production process for general warehouse production. The fields in the area of the lot size-dependent in-house production time are to be populated when the…
The correct answer is C. In the course of basic dates scheduling with requirements planning, dependent requirements request. See the full explanation below for the reasoning.
Question
In SAP ECC, you want to map an in-house production process for general warehouse production. The fields in the area of the lot size-dependent in-house production time are to be populated when the material master for the final product is created. These fields can be maintained by updating from the scheduling result for the associated routing. You now think that there could be significant changes to the production times in the routing and decide against updating the material master. What problem could this lead to?
Options
- ASubsequent capacity planning is no longer possible due to the obsolete scheduling parameters.
- BRequirements planning runs up against an exception message in basic dates scheduling because
- CIn the course of basic dates scheduling with requirements planning, dependent requirements request
- DLead time scheduling, which occurs by the time that a planned order is converted into a production
How the community answered
(24 responses)- A17% (4)
- B4% (1)
- C71% (17)
- D8% (2)