C_TS4CO_1909 · Question #131
What do you get if you mark a standard price cost estimate? There are TWO correct answers for this question
The correct answer is B. A new status in the cost estimate D. A future standard price. See the full explanation below for the reasoning.
Question
What do you get if you mark a standard price cost estimate? There are TWO correct answers for this question
Options
- AA cost-based CO-PA document for material revaluation
- BA new status in the cost estimate
- CAn accounting document for material ledger
- DA future standard price
How the community answered
(38 responses)- A5% (2)
- B82% (31)
- C13% (5)