SAP
C_TS4CO_1909 · Question #130
For which objects can you revaluate activities and business processes at actual prices? There are THREE correct answers for this question
The correct answer is A. Work breakdown structure elements C. Profit centers E. Profitability segments. See the full explanation below for the reasoning.
Question
For which objects can you revaluate activities and business processes at actual prices? There are THREE correct answers for this question
Options
- AWork breakdown structure elements
- BCost centers
- CProfit centers
- DWork centers
- EProfitability segments
How the community answered
(40 responses)- A78% (31)
- B15% (6)
- D8% (3)