Which object do you configure to reuse material cost estimate for the costing process?
The correct answer is B. Transfer control. See the full explanation below for the reasoning.
Question
Which object do you configure to reuse material cost estimate for the costing process?
Options
- AValuation variant
- BTransfer control
- CQuantity structure control
- DGroup costing
How the community answered
(42 responses)- A5% (2)
- B71% (30)
- C14% (6)
- D10% (4)
Community Discussion