C_TS4CO_1909 · Question #132
What do you use to map the primary cost component split to the production cost component structure?
The correct answer is C. Cost Component groups. See the full explanation below for the reasoning.
Question
What do you use to map the primary cost component split to the production cost component structure?
Options
- AAssignment scheme
- BTransfer structure
- CCost Component groups
- DAllocation structure
How the community answered
(18 responses)- B6% (1)
- C83% (15)
- D11% (2)