C_TS410_1809 · Question #53

What can a planned order be converted to? There are TWO correct answers for this Question.

The correct answer is B. A production order D. A purchase requisition. See the full explanation below for the reasoning.

Question

What can a planned order be converted to? There are TWO correct answers for this Question.

Options

  • AA planned independent requirement
  • BA production order
  • CA purchase order
  • DA purchase requisition

How the community answered

(46 responses)
  • A
    7% (3)
  • B
    74% (34)
  • C
    20% (9)

Community Discussion

No community discussion yet for this question.

Full C_TS410_1809 Practice