Which of the following sequences of purchase-to-pay process steps is valid?

The correct answer is C. Determination of requirements .Vendor selection , Purchase order handling .Goods. See the full explanation below for the reasoning.

Question

Which of the following sequences of purchase-to-pay process steps is valid?

Options

  • ASource of supply determination .Vendor selection , Determination of requirements Purchase order
  • BVendor selection .Source of supply determination , Purchase order monitoring .Goods
  • CDetermination of requirements .Vendor selection , Purchase order handling .Goods
  • DDetermination of requirements .Purchase order handling . Handling of payments .Goods

How the community answered

(44 responses)
  • A
    16% (7)
  • B
    5% (2)
  • C
    70% (31)
  • D
    9% (4)