SAP
C_TS410_1809 · Question #52
Which of the following sequences of purchase-to-pay process steps is valid?
The correct answer is C. Determination of requirements .Vendor selection , Purchase order handling .Goods. See the full explanation below for the reasoning.
Question
Which of the following sequences of purchase-to-pay process steps is valid?
Options
- ASource of supply determination .Vendor selection , Determination of requirements Purchase order
- BVendor selection .Source of supply determination , Purchase order monitoring .Goods
- CDetermination of requirements .Vendor selection , Purchase order handling .Goods
- DDetermination of requirements .Purchase order handling . Handling of payments .Goods
How the community answered
(44 responses)- A16% (7)
- B5% (2)
- C70% (31)
- D9% (4)
Community Discussion