SAP
C_TS410_1809 · Question #71
What can a successful MRP run create?
The correct answer is A. Dependent requirements. See the full explanation below for the reasoning.
Question
What can a successful MRP run create?
Options
- ADependent requirements
- BReservations
- CPurchase orders
- DPlanned independent requirements
How the community answered
(40 responses)- A83% (33)
- B3% (1)
- C5% (2)
- D10% (4)
Community Discussion