nerdexam
SAP

C_TS410_1809 · Question #71

What can a successful MRP run create?

The correct answer is A. Dependent requirements. See the full explanation below for the reasoning.

Question

What can a successful MRP run create?

Options

  • ADependent requirements
  • BReservations
  • CPurchase orders
  • DPlanned independent requirements

How the community answered

(40 responses)
  • A
    83% (33)
  • B
    3% (1)
  • C
    5% (2)
  • D
    10% (4)

Community Discussion

No community discussion yet for this question.

Full C_TS410_1809 Practice