nerdexam
SAP

C_TS410_1809 · Question #22

What function compares assigned funds to the budget of a work breakdown structures (WBS) element?

The correct answer is D. Settlement. See the full explanation below for the reasoning.

Question

What function compares assigned funds to the budget of a work breakdown structures (WBS) element?

Options

  • ACost forecast
  • BResults analysis
  • CAvailability control
  • DSettlement

How the community answered

(50 responses)
  • A
    6% (3)
  • B
    2% (1)
  • C
    12% (6)
  • D
    80% (40)

Community Discussion

No community discussion yet for this question.

Full C_TS410_1809 Practice