SAP
C_TS410_1809 · Question #22
What function compares assigned funds to the budget of a work breakdown structures (WBS) element?
The correct answer is D. Settlement. See the full explanation below for the reasoning.
Question
What function compares assigned funds to the budget of a work breakdown structures (WBS) element?
Options
- ACost forecast
- BResults analysis
- CAvailability control
- DSettlement
How the community answered
(50 responses)- A6% (3)
- B2% (1)
- C12% (6)
- D80% (40)
Community Discussion
No community discussion yet for this question.