Which of the following can promptly identify commitments for a project that are too high and trigger various actions in response? Please choose the correct answer.

The correct answer is B. Availability control. See the full explanation below for the reasoning.

Question

Which of the following can promptly identify commitments for a project that are too high and trigger various actions in response? Please choose the correct answer.

Options

  • ATolerance limit
  • BAvailability control
  • CTime horizon
  • DBudget plan

How the community answered

(44 responses)
  • A
    7% (3)
  • B
    80% (35)
  • C
    11% (5)
  • D
    2% (1)