nerdexam
SAP

C_TPLM22_64 · Question #78

Which of the available capacity leveling methods for networks/activities allows you to select a particular work center and display a capacity load curve that shows both the capacity requirements and…

The correct answer is B. Project planning board. See the full explanation below for the reasoning.

Question

Which of the available capacity leveling methods for networks/activities allows you to select a particular work center and display a capacity load curve that shows both the capacity requirements and the available capacity? Please choose the correct answer.

Options

  • AWorkforce planning board
  • BProject planning board
  • CWork center planning board
  • DCapacity planning board

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    80% (16)
  • C
    10% (2)
  • D
    5% (1)

Community Discussion

No community discussion yet for this question.

Full C_TPLM22_64 Practice