Which technique is one of the ways to measure the earned value where each milestone corresponds to a percentage of work completed in an activity or a WBS element in progress analysis? Please choose…

The correct answer is C. Milestone technique. See the full explanation below for the reasoning.

Question

Which technique is one of the ways to measure the earned value where each milestone corresponds to a percentage of work completed in an activity or a WBS element in progress analysis? Please choose the correct answer.

Options

  • AProject technique
  • BTrend technique
  • CMilestone technique
  • DPeriod indicator technique

How the community answered

(37 responses)
  • A
    5% (2)
  • B
    8% (3)
  • C
    84% (31)
  • D
    3% (1)