SAP
C_TPLM22_64 · Question #74
Consider a scenario in easy cost planning where you plan dates and resources in network activities and the system automatically determines the corresponding planned costs as part of network costing…
The correct answer is A. Primary costs for material components B. Activity inputs for internally-processed activities C. Primary costs for general costs activities. See the full explanation below for the reasoning.
Question
Consider a scenario in easy cost planning where you plan dates and resources in network activities and the system automatically determines the corresponding planned costs as part of network costing. In this scenario planned costs are determined for which of the following? There are 3 correct answers to this question.
Options
- APrimary costs for material components
- BActivity inputs for internally-processed activities
- CPrimary costs for general costs activities
- DPrimary costs for service activities
How the community answered
(36 responses)- A78% (28)
- D22% (8)
Community Discussion
No community discussion yet for this question.