nerdexam
SAP

C_TPLM22_64 · Question #71

When using networks and activities, planned costs are automatically calculated based on the resource requirements identified for which of the following? There are 2 correct answers to this question.

The correct answer is A. Operations D. Activities. See the full explanation below for the reasoning.

Question

When using networks and activities, planned costs are automatically calculated based on the resource requirements identified for which of the following? There are 2 correct answers to this question.

Options

  • AOperations
  • BTasks
  • CWBS
  • DActivities

How the community answered

(16 responses)
  • A
    75% (12)
  • B
    19% (3)
  • C
    6% (1)

Community Discussion

No community discussion yet for this question.

Full C_TPLM22_64 Practice