C_TPLM22_64 · Question #71
When using networks and activities, planned costs are automatically calculated based on the resource requirements identified for which of the following? There are 2 correct answers to this question.
The correct answer is A. Operations D. Activities. See the full explanation below for the reasoning.
Question
When using networks and activities, planned costs are automatically calculated based on the resource requirements identified for which of the following? There are 2 correct answers to this question.
Options
- AOperations
- BTasks
- CWBS
- DActivities
How the community answered
(16 responses)- A75% (12)
- B19% (3)
- C6% (1)