Which scheduling calculates the latest start and finish dates for all activities? Please choose the correct answer.

The correct answer is C. Forward scheduling. See the full explanation below for the reasoning.

Question

Which scheduling calculates the latest start and finish dates for all activities? Please choose the correct answer.

Options

  • ABackward scheduling
  • BNetwork based scheduling
  • CForward scheduling
  • DProject based scheduling

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    7% (2)
  • C
    78% (21)
  • D
    11% (3)