In internal processing which views allow you to easily and quickly assign persons to activities and use various data (availability of the person from Human Resources, the total work planned for that…
The correct answer is A. Work center view D. Project view. See the full explanation below for the reasoning.
Question
In internal processing which views allow you to easily and quickly assign persons to activities and use various data (availability of the person from Human Resources, the total work planned for that person, or the activity date)? There are 2 correct answers to this question.
Options
- AWork center view
- BResource view
- CAssignment view
- DProject view
How the community answered
(44 responses)- A73% (32)
- B18% (8)
- C9% (4)