C_TPLM22_64 · Question #58

Which scenario does not allow you to access the project team of the higher-level WBS element during ''workforce planning''? Please choose the correct answer.

The correct answer is D. If a WBS element does have its own project team. See the full explanation below for the reasoning.

Question

Which scenario does not allow you to access the project team of the higher-level WBS element during ''workforce planning''? Please choose the correct answer.

Options

  • AProject team is in the higher level in hierarchy to WBS element
  • BIf a WBS element does not have its own project team
  • CWBS element is in the higher level
  • DIf a WBS element does have its own project team

How the community answered

(44 responses)
  • A
    2% (1)
  • B
    11% (5)
  • C
    5% (2)
  • D
    82% (36)