C_TPLM22_64 · Question #56
In your project, you choose internal activities to confirm actual dates. After you partially confirmed an internal activity, you want that the actual start will be considered for the calculation of…
The correct answer is A. Deactivate the shift order indicator in Parameters for Network Scheduling. See the full explanation below for the reasoning.
Question
In your project, you choose internal activities to confirm actual dates. After you partially confirmed an internal activity, you want that the actual start will be considered for the calculation of the earliest scheduled dates. How can you implement this? Please choose the correct answer.
Options
- ADeactivate the shift order indicator in Parameters for Network Scheduling.
- BActivate the shift order indicator in Parameters for Network Scheduling.
- CActivate the actual date consider indicator in Parameters for Network Scheduling.
- DDeactivate actual date consider indicator in Parameters for Network Scheduling.
How the community answered
(38 responses)- A82% (31)
- B5% (2)
- C3% (1)
- D11% (4)