The correct answer is C. Reduction. See the full explanation below for the reasoning.
Question
How do you reduce the scheduled duration of internally-processed activities if the time period within which the activities are to be scheduled is not long enough to process all activities? Please choose the correct answer.
Options
- AMilestones
- BCapacity breech
- CReduction
- DScheduling breech