nerdexam
SAP

C_TPLM22_64 · Question #34

Where else should you make manual changes; if you assign bill of materials (BOM) items to a network activity manually by exploding the BOM and then changed the BOM? Please choose the correct answer.

The correct answer is D. Network. See the full explanation below for the reasoning.

Question

Where else should you make manual changes; if you assign bill of materials (BOM) items to a network activity manually by exploding the BOM and then changed the BOM? Please choose the correct answer.

Options

  • ACost object
  • BMaterial view
  • CAssignments
  • DNetwork

How the community answered

(49 responses)
  • A
    14% (7)
  • B
    2% (1)
  • C
    8% (4)
  • D
    76% (37)

Community Discussion

No community discussion yet for this question.

Full C_TPLM22_64 Practice