C_TPLM22_64 · Question #34
Where else should you make manual changes; if you assign bill of materials (BOM) items to a network activity manually by exploding the BOM and then changed the BOM? Please choose the correct answer.
The correct answer is D. Network. See the full explanation below for the reasoning.
Question
Where else should you make manual changes; if you assign bill of materials (BOM) items to a network activity manually by exploding the BOM and then changed the BOM? Please choose the correct answer.
Options
- ACost object
- BMaterial view
- CAssignments
- DNetwork
How the community answered
(49 responses)- A14% (7)
- B2% (1)
- C8% (4)
- D76% (37)