Which function allows you to make cross-project changes to fields pertaining to project definitions, WBS elements, networks, activities, milestones and relationships? Please choose the correct answer.
The correct answer is D. Mass change function. See the full explanation below for the reasoning.
Question
Which function allows you to make cross-project changes to fields pertaining to project definitions, WBS elements, networks, activities, milestones and relationships? Please choose the correct answer.
Options
- AMass document function
- BAuthorization function
- CWork function
- DMass change function
How the community answered
(50 responses)- A6% (3)
- B2% (1)
- C8% (4)
- D84% (42)