You have implemented automatic requirements grouping for projects. Once you check the materials turbine and fittings you realize that the requirements are grouped for turbine but not for fittings…

The correct answer is C. The MRP Group for fittings is deactivated for grouping. See the full explanation below for the reasoning.

Question

You have implemented automatic requirements grouping for projects. Once you check the materials turbine and fittings you realize that the requirements are grouped for turbine but not for fittings. What might be the reason? Please choose the correct answer.

Options

  • AThe grouping indicator of the top WBS element is set to a single MRP Group.
  • BThe network is set to no grouping for specific MRP Groups.
  • CThe MRP Group for fittings is deactivated for grouping.
  • DThe project definition is set to no project stock.

How the community answered

(19 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    79% (15)
  • D
    11% (2)