What does ''E'' determine in account assignment while using consumption posting indicator to determine the controlling object for the sales item? Please choose the correct answer.
The correct answer is C. E determines that the sales order is a cost object. See the full explanation below for the reasoning.
Question
What does ''E'' determine in account assignment while using consumption posting indicator to determine the controlling object for the sales item? Please choose the correct answer.
Options
- AE determines that the sales order is a controlling object
- BE determines that the sales order is a project is a controlling object
- CE determines that the sales order is a cost object
- DE determines that the sales order items are relevant for delivery through sales and distribution
How the community answered
(54 responses)- A15% (8)
- B6% (3)
- C72% (39)
- D7% (4)