C_TPLM22_64 · Question #18

Which of the following can be derived automatically when you carry out scheduling in projects with networks? There are 2 correct answers to this question.

The correct answer is A. WBS element dates C. Activity dates. See the full explanation below for the reasoning.

Question

Which of the following can be derived automatically when you carry out scheduling in projects with networks? There are 2 correct answers to this question.

Options

  • AWBS element dates
  • BScheduling dates
  • CActivity dates
  • DNetwork dates

How the community answered

(43 responses)
  • A
    72% (31)
  • B
    19% (8)
  • D
    9% (4)