SAP
C_TPLM22_64 · Question #15
What is the flag used for WBS elements for which you want to plan costs? Please choose the correct answer.
The correct answer is C. Planning elements. See the full explanation below for the reasoning.
Question
What is the flag used for WBS elements for which you want to plan costs? Please choose the correct answer.
Options
- ABilling elements
- BAssignment elements
- CPlanning elements
- DRevenue elements
How the community answered
(36 responses)- A3% (1)
- B11% (4)
- C81% (29)
- D6% (2)
Community Discussion