C_TPLM22_64 · Question #13

Assume you have information on sources of supply, quantities, and prices and you have decided to use unit costing to produce a cost plan per WBS element. Which of the following costs can be planned?…

The correct answer is A. Each material B. Cost element level D. Each internal activity. See the full explanation below for the reasoning.

Question

Assume you have information on sources of supply, quantities, and prices and you have decided to use unit costing to produce a cost plan per WBS element. Which of the following costs can be planned? There are 3 correct answers to this question.

Options

  • AEach material
  • BCost element level
  • CInternal service
  • DEach internal activity

How the community answered

(48 responses)
  • A
    73% (35)
  • C
    27% (13)

Community Discussion

No community discussion yet for this question.