C_TPLM22_64 · Question #1

Which of the following costs are automatically calculated based on the resource requirements identified for activities and operations when using networks and activities? Please choose the correct…

The correct answer is C. Planned costs. See the full explanation below for the reasoning.

Question

Which of the following costs are automatically calculated based on the resource requirements identified for activities and operations when using networks and activities? Please choose the correct answer.

Options

  • AManual costs
  • BActual costs
  • CPlanned costs
  • DElement costs

How the community answered

(41 responses)
  • A
    12% (5)
  • B
    7% (3)
  • C
    78% (32)
  • D
    2% (1)