SAP
C_TPLM22_64 · Question #1
Which of the following costs are automatically calculated based on the resource requirements identified for activities and operations when using networks and activities? Please choose the correct…
The correct answer is C. Planned costs. See the full explanation below for the reasoning.
Question
Which of the following costs are automatically calculated based on the resource requirements identified for activities and operations when using networks and activities? Please choose the correct answer.
Options
- AManual costs
- BActual costs
- CPlanned costs
- DElement costs
How the community answered
(41 responses)- A12% (5)
- B7% (3)
- C78% (32)
- D2% (1)
Community Discussion
No community discussion yet for this question.