C_ACTIVATE13 · Question #61

What is the objective of a sprint retrospective meeting?

The correct answer is A. Improve the scrum process. See the full explanation below for the reasoning.

Question

What is the objective of a sprint retrospective meeting?

Options

  • AImprove the scrum process
  • BReview and prioritize the backlog
  • CProvide formal feedback to the project manager
  • DDefine the stakeholder management approach

How the community answered

(41 responses)
  • A
    76% (31)
  • B
    7% (3)
  • C
    15% (6)
  • D
    2% (1)