C_ACTIVATE13 · Question #61
What is the objective of a sprint retrospective meeting?
The correct answer is A. Improve the scrum process. See the full explanation below for the reasoning.
Question
What is the objective of a sprint retrospective meeting?
Options
- AImprove the scrum process
- BReview and prioritize the backlog
- CProvide formal feedback to the project manager
- DDefine the stakeholder management approach
How the community answered
(41 responses)- A76% (31)
- B7% (3)
- C15% (6)
- D2% (1)