How would you describe the realise phase in the "new implementation of SAP S/4HANA" transition path?

The correct answer is D. Configure and adjust custom code. See the full explanation below for the reasoning.

Question

How would you describe the realise phase in the "new implementation of SAP S/4HANA" transition path?

Options

  • AConfigure
  • BConfigure and develop
  • CConfiguration copy
  • DConfigure and adjust custom code

How the community answered

(39 responses)
  • A
    3% (1)
  • B
    15% (6)
  • C
    8% (3)
  • D
    74% (29)